<?xml version="1.0" encoding="UTF-8"?>
<article article-type="research-article" dtd-version="1.3" xml:lang="ru" xmlns:xlink="http://www.w3.org/1999/xlink" xmlns:mml="http://www.w3.org/1998/Math/MathML" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="https://metafora.rcsi.science/xsd_files/journal3.xsd">
  <front>
    <journal-meta>
      <journal-id journal-id-type="publisher-id">moitvivt</journal-id>
      <journal-title-group>
        <journal-title xml:lang="ru">Моделирование, оптимизация и информационные технологии</journal-title>
        <trans-title-group xml:lang="en">
          <trans-title>Modeling, Optimization and Information Technology</trans-title>
        </trans-title-group>
      </journal-title-group>
      <issn pub-type="epub">2310-6018</issn>
      <publisher>
        <publisher-name>Издательство</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="doi">10.26102/2310-6018/2025.49.2.037</article-id>
      <article-id pub-id-type="custom" custom-type="elpub">1941</article-id>
      <title-group>
        <article-title xml:lang="ru">Алгоритм оптимизации ресурсного обеспечения проекта с учетом нечетких рекомендаций экспертов по срокам начала работ</article-title>
        <trans-title-group xml:lang="en">
          <trans-title>Algorithm for optimizing project resource allocation considering fuzzy expert recommendations on task start times</trans-title>
        </trans-title-group>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author" corresp="yes">
          <name-alternatives>
            <name name-style="eastern" xml:lang="ru">
              <surname>Азарнова</surname>
              <given-names>Татьяна Васильевна</given-names>
            </name>
            <name name-style="western" xml:lang="en">
              <surname>Azarnova</surname>
              <given-names>Tatiana Vasilievna</given-names>
            </name>
          </name-alternatives>
          <email>ivdas92@mail.ru</email>
          <xref ref-type="aff">aff-1</xref>
        </contrib>
        <contrib contrib-type="author">
          <contrib-id contrib-id-type="orcid">0000-0001-6588-3682</contrib-id>
          <name-alternatives>
            <name name-style="eastern" xml:lang="ru">
              <surname>Иванова</surname>
              <given-names>Екатерина Вячеславовна</given-names>
            </name>
            <name name-style="western" xml:lang="en">
              <surname>Ivanova</surname>
              <given-names>Ekaterina Vyacheslavovna</given-names>
            </name>
          </name-alternatives>
          <email>ekaterina.v.ivanova@inbox.ru</email>
          <xref ref-type="aff">aff-2</xref>
        </contrib>
      </contrib-group>
      <aff-alternatives id="aff-1">
        <aff xml:lang="ru">Воронежский государственный университет</aff>
        <aff xml:lang="en">Voronezh State University</aff>
      </aff-alternatives>
      <aff-alternatives id="aff-2">
        <aff xml:lang="ru">Воронежский государственный университет</aff>
        <aff xml:lang="en">Voronezh State University</aff>
      </aff-alternatives>
      <pub-date pub-type="epub">
        <day>01</day>
        <month>01</month>
        <year>2026</year>
      </pub-date>
      <volume>1</volume>
      <issue>1</issue>
      <elocation-id>10.26102/2310-6018/2025.49.2.037</elocation-id>
      <permissions>
        <copyright-statement>Copyright © Авторы, 2026</copyright-statement>
        <copyright-year>2026</copyright-year>
        <license license-type="creative-commons-attribution" xlink:href="https://creativecommons.org/licenses/by/4.0/">
          <license-p>This work is licensed under a Creative Commons Attribution 4.0 International License</license-p>
        </license>
      </permissions>
      <self-uri xlink:href="https://moitvivt.ru/ru/journal/article?id=1941"/>
      <abstract xml:lang="ru">
        <p>В статье предлагается алгоритм оценки ресурсного обеспечения проекта с учетом различных нечетких экспертных рекомендаций по срокам начала выполнения работ в пределах резервных ограничений и выбора оптимального варианта экспертных рекомендаций. Для определения резервных ограничений по срокам начала и окончания работ проекта используется классический алгоритм нахождения критического пути. Экспертные рекомендации по срокам начала работ моделируются в виде нечетких трапециевидных или треугольных чисел, заданных на оси времени. На основе нечетких сроков начала и окончания работ проекта формируется нечеткое представление вероятности того, что работа будет осуществляться в определенный момент времени. Построение альфа-срезов для нечеткого представления вероятности позволяет выделить промежутки в рамках резервных ограничений для сроков выполнения работ, в пределах которых работа будет осуществляться на определенном уровне нечеткой вероятности, и спланировать ресурсы на данный период времени. Полученные результаты позволяют оценить: оптимальные с точки зрения распределения ресурсов экспертные рекомендации по срокам начала работ; минимизировать привлечение субподряда для выполнения работ проекта; рассчитать затраты, связанные с привлечением субподряда. Предложенное алгоритмическое и программное обеспечение может служить эффективным средством поддержки принятия решений при реализации многокомпонентных проектов.</p>
      </abstract>
      <trans-abstract xml:lang="en">
        <p>This article proposes an algorithm for evaluating project resource allocation that takes into account various fuzzy expert recommendations regarding the start times of tasks within float constraints, aiming to select the optimal set of expert suggestions. To determine the float constraints for task start and finish times, the classical critical path method is used. Expert recommendations on task start times are modeled as fuzzy trapezoidal or triangular numbers defined along the time axis. Based on the fuzzy start and finish times of project tasks, a fuzzy representation of the probability that a task will be performed at a specific moment is constructed. Building alpha-cuts for this fuzzy probability representation allows the identification of intervals, within float constraints, during which a task is likely to be performed at a certain level of fuzzy probability, thus enabling resource planning for those periods. The obtained results allow for: evaluating the expert recommendations that are optimal in terms of resource distribution; minimizing subcontracting needs for task execution; and calculating the associated subcontracting costs. The proposed algorithmic and software solution can serve as an effective decision support tool in the implementation of multi-component projects.</p>
      </trans-abstract>
      <kwd-group xml:lang="ru">
        <kwd>сетевой граф проекта</kwd>
        <kwd>критический путь</kwd>
        <kwd>нечеткие экспертные рекомендации</kwd>
        <kwd>сроки выполнения работ проекта</kwd>
        <kwd>ресурсная оптимизация проекта</kwd>
      </kwd-group>
      <kwd-group xml:lang="en">
        <kwd>network graph of the project</kwd>
        <kwd>critical path</kwd>
        <kwd>fuzzy expert recommendations</kwd>
        <kwd>work completion dates on project</kwd>
        <kwd>project resource optimization</kwd>
      </kwd-group>
      <funding-group>
        <funding-statement xml:lang="ru">Исследование выполнено без спонсорской поддержки.</funding-statement>
        <funding-statement xml:lang="en">The study was performed without external funding.</funding-statement>
      </funding-group>
    </article-meta>
  </front>
  <back>
    <ref-list>
      <title>References</title>
      <ref id="cit1">
        <label>1</label>
        <mixed-citation xml:lang="ru">Brucker P., Drexl A., Möhring R., Neumann K., Pesch E. Resource-Constrained Project Scheduling: Notation, Classification, Models, and Methods. European Journal of Operational Research. 1999;112(1):3–41. https://doi.org/10.1016/S0377-2217(98)00204-5</mixed-citation>
      </ref>
      <ref id="cit2">
        <label>2</label>
        <mixed-citation xml:lang="ru">Kreter S., Schutt A., Stuckey P.J. Using Constraint Programming for Solving RCPSP/Max-Cal. Constraints. 2017;22(3):432–462. https://doi.org/10.1007/s10601-016-9266-6</mixed-citation>
      </ref>
      <ref id="cit3">
        <label>3</label>
        <mixed-citation xml:lang="ru">Vanhoucke M., Coelho J. Resource-Constrained Project Scheduling with Activity Splitting and Setup Times. Computers &amp; Operations Research. 2019;109:230–249. https://doi.org/10.1016/j.cor.2019.05.004</mixed-citation>
      </ref>
      <ref id="cit4">
        <label>4</label>
        <mixed-citation xml:lang="ru">Chang T.C., Ibbs C.W., Crandall K.C. Network Resource Allocation with Support of a Fuzzy Expert System. Journal of Construction Engineering and Management. 1990;116(2):239–260. https://doi.org/10.1061/(ASCE)0733-9364(1990)116:2(239)</mixed-citation>
      </ref>
      <ref id="cit5">
        <label>5</label>
        <mixed-citation xml:lang="ru">Rezakhani P. Project Scheduling and Performance Prediction: A Fuzzy-Bayesian Network Approach. Engineering, Construction and Architectural Management. 2022;29(6):2233–2244. https://doi.org/10.1108/ECAM-07-2020-0540</mixed-citation>
      </ref>
      <ref id="cit6">
        <label>6</label>
        <mixed-citation xml:lang="ru">S A.S.P., Paul A. Fuzzy Logic in Construction Project Scheduling: A Review. International Research Journal of Engineering and Technology. 2008;5(11):752–755.</mixed-citation>
      </ref>
      <ref id="cit7">
        <label>7</label>
        <mixed-citation xml:lang="ru">Dorn J., Kerr R., Thalhammer G. Reactive Scheduling: Improving the Robustness of Schedules and Restricting the Effects of Shop Foor Disturbances by Fuzzy Reasoning. International Journal of Human–Computer Studies. 1995;42(6):687–704. https://doi.org/10.1006/ijhc.1995.1031</mixed-citation>
      </ref>
      <ref id="cit8">
        <label>8</label>
        <mixed-citation xml:lang="ru">Cheng Ch.-B., Lo Ch.-Yu. Multi-Project Scheduling by Fuzzy Combinatorial Auction. In: 2017 3rd IEEE International Conference on Cybernetics (CYBCONF), 21–23 June 2017, Exeter, UK. IEEE; 2017. P. 1–6. https://doi.org/10.1109/CYBConf.2017.7985794</mixed-citation>
      </ref>
      <ref id="cit9">
        <label>9</label>
        <mixed-citation xml:lang="ru">Ladnykh I.A., Ibadov N. Estimating the Duration of Construction Works Using Fuzzy Modeling to Assess the Impact of Risk Factors. Applied Sciences. 2024;14(9). https://doi.org/10.3390/app14093847</mixed-citation>
      </ref>
      <ref id="cit10">
        <label>10</label>
        <mixed-citation xml:lang="ru">Plebankiewicz E., Karcińska P. Model for Supporting Construction Workforce Planning Based on the Theory of Fuzzy Sets. Applied Sciences. 2024;14(4). https://doi.org/10.3390/app14041655</mixed-citation>